BQE CORE Blog – Time Tracking and Project Management Software

How to do AIA Invoicing & Billing: Formats, Templates & Examples

Written by Lucas Gray | Jan 21, 2026
Master AIA invoicing with our complete guide. Learn to fill out G702 and G703 forms, review real billing math, and download free AIA-style templates. See mid-project and closeout examples to understand how the forms evolve.

Inside this article:


What Is AIA Billing?

AIA billing is a standard method for handling payments on construction projects. The American Institute of Architects (AIA) created it for jobs where the owner pays the contractor over time. Many contracts require AIA billing (or AIA-style billing) when a project owner pays a contractor at particular milestones.

AIA billing is based on the progress billing model, in which contractors are paid as they complete parts of a project rather than receiving a single large payment at the end. AIA is one particular type of overall architecture invoicing. 

The American Institute of Architects (AIA) created AIA billing for projects where an architect collaborates with a project owner and oversees the work of the construction contractor. The AIA Contract Documents outline the basic roles of each party in the payment process. The two main ones are A201 (General Conditions of the Contract for Construction) and B101 (Standard Form of Agreement Between Owner and Architect). The contractor prepares the pay application, the architect reviews and certifies it, and the owner releases payment based on that certification.

Over time, AIA billing has become the industry standard for progress payments because it’s clear, structured, and consistent. Today, many construction projects, even those without an architect, use AIA billing forms to keep billing organized and transparent. It is one of the most widely accepted billing and invoicing methods in the construction and design space. 

Understanding AIA billing can open doors to larger contracts and public projects, where progress billing and AIA invoicing are often standard requirements.

Understanding the AIA billing format

The AIA billing format uses two forms — the G702 and G703 — that contractors submit each month to request payment. The G702 summarizes project progress and calculates how much the contractor is billing for that period, while the G703 provides the detailed breakdown behind those totals.

Most AIA-type projects are based on a lump-sum (or stipulated-sum) contract, meaning the owner and contractor agree to one fixed price for the entire project. Instead of billing for actual costs, the contractor earns payment based on the percentage of work completed toward that agreed total.

Before construction starts, the contractor and owner create a schedule of values (SOV) that divides the total contract price into specific parts — such as site work, framing, and finishes. Each part is assigned a dollar value.

Every month, the contractor uses the SOV to calculate progress and prepare two forms:

  • AIA G702, Application and Certificate for Payment: This is the “pay application” (or “pay app”) that the contractor sends to the project manager or architect. It summarizes the percentage of work the contractor completed during the month and gives an overview of total progress. The architect reviews the form and certifies that the reported work and payment amount are reasonable.
  • AIA G703, Continuation Sheet: This breaks down costs in support of the G702 form. The G703 organizes labor and material costs into line items based on the project’s schedule of values (SOV). It shows how much work is complete, how much remains, and calculates the figures that appear on the G702 summary.

The two AIA-style templates offered later in this article follow a similar structure to official AIA forms. They’re intended for training, estimating, or projects in which AIA-style documentation is acceptable. However, they are not official AIA documents and should not be used when a contract specifically requires licensed AIA forms.

Form G702: Application & Certification for Payment

Form G702 is a construction pay application to track project progress. It calculates how much the contractor earns each billing cycle, and it turns on-site progress into a record of earned value. The contractor reports work completed, subtracts prior payments, and shows the new amount due.

The G702 provides a monthly snapshot of the project’s financial status. It tracks total work completed, prior payments, and retainage to determine what’s owed for the current billing period. Each section guides the contractor in turning project progress into a running billing record.

“Each month, the contractor updates the same running totals, so the G702 reflects both the cumulative value of the project and acts like a monthly invoice,” says Austin Miller, Chief Marketing Officer at BQE. “As pay applications continue through the project, each G702 builds on the one before it.”

For every G702, an architect or other designated signatory reviews the figures to confirm that the contractor’s calculations reasonably reflect the work that’s been done. Their signature certifies the payment application and formally approves the payment request.

Key fields on the G702 include:
  • Original Contract Sum: Lists the total contract value at the start of the project.
  • Approved Change Orders (COs): Lists any contract adjustments that increase or decrease the original sum
  • Adjusted Contract Sum: Adds the original contract sum to any COs to report the contract total after all approved changes.
  • Total Completed and Stored to Date: Lists the cumulative value of all the work the contractor has performed to date, along with the value of any materials they purchased but haven’t installed yet.
  • Retainage: Lists the portion of each payment the owner holds back until the job reaches a certain milestone.
  • Current Payment Due: Lists the new amount that the contractor is billing for this period.
  • Certification: Signed approval by the architect or owner authorizing payment.

 


Form G703: Continuation Sheet / Schedule of Values

The G703 accompanies the G702 and provides the detailed backup for the totals on the payment application. Each row lists a specific phase or trade from the project’s original Schedule of Values (SOV), along with related materials, and tracks the cost of work completed and billed for that item.

Each row on the G703 matches a specific part of the project that comes directly from the SOV that the contractor and owner created before signing the contract. For example, a line might cover “Electrical Work” or “Framing.” For each row, the columns track how much money the contractor has spent over time for that phase, including the value of any materials purchased.

All these amounts add up to Column G, labeled “Total Completed and Stored to Date.” This column shows how much work and material value the contractor has earned up to the current billing period.

At the bottom of the sheet, the totals from the G703 feed directly into the G702. The sum of the “Total Completed and Stored to Date” column becomes Line 4 on the G702 (“Total Completed & Stored to Date”). That’s to ensure the G702 reflects accurate, itemized progress from the schedule of values.

Here’s an overview of key fields from the G703:

  • Scheduled Value: Lists the dollar amount assigned to each phase or trade in the project’s schedule of values
  • Work Completed This Period: Shows how much new work the contractor finished and billed for during the current pay cycle.
  • Total Completed and Stored to Date (Column G): Summarizes all work completed and materials stored to date. This value transfers directly to Line 4 on the G702.
  • Retainage: Records the portion of payment the owner withholds until the contractor reaches specific milestones or completes the job.
  • Balance to Finish: Shows the remaining contract value for each line item after subtracting completed and retained amounts.

In short, while the G702 presents the project’s financial summary, the G703 provides detailed line-by-line proof that supports the contractor's calculations.

Other AIA Pay-Application Variants

AIA offers other pay application forms that adapt the G702 and G703 formats to accommodate different payment methods and different working relationships. Some forms fit cost-of-the-work contracts, while others apply to subcontractors, joint ventures, or design-build teams that manage both design and construction.

Here’s a summary of other AIA pay application types. Remember, all AIA contract forms, including the G702 and G703, are copyrighted materials owned by the AIA.

AIA G702S/G703S: Subcontractor Versions

The form titles are:

  • G702S, Application and Certificate for Payment, Contractor-Subcontractor Version
  • G703S, Continuation Sheet, Contractor-Subcontractor Version

When to use: Subcontractors use these forms to bill the general contractor for their work under a standard “lump-sum” contract. They follow the same AIA format the general contractor later uses to bill the owner.  

How it’s different from G702/G703: The layout and calculations are identical to the standard forms, but the language changes to reflect the different relationships between the entities. For example, the G702S replaces “Owner” with “Contractor” and “Contractor” with “Subcontractor.” In this case, the general contractor certifies the pay application instead of the architect.

AIA G702GMP-2021 and G703CW-2021

The form titles are: 

  • G702GMP-2021: Application and Certificate for Payment for Cost of the Work Projects with a Guaranteed Maximum Price (GMP)
  • G703CW-2021: Continuation Sheet for Cost of the Work Projects (paired sheet regardless of GMP)

When to use: Contractors use these forms for cost-of-the-work projects that include a Guaranteed Maximum Price (GMP). In a cost-of-the-work contract, the contractor bills for actual project costs, such as labor, materials, subcontractors, and general conditions, rather than a percentage of completed work. The GMP sets a cap on how much the project owner will pay, in order to protect the owner from unexpected cost overruns.

How it’s different from G702/G703: To fit this payment model, the forms replace all “Contract Sum” or “Owner–Contractor Sum” references with “Guaranteed Maximum Price.” For instance, Line 1 on the G702GMP-2021 reads “Original Guaranteed Maximum Price” instead of “Original Contract Sum.” This change makes the form align with the financial limits defined in a GMP contract.

Beyond language, the continuation sheet, the G703CW-2021, includes additional columns for each cost item that allow the contractor to show both estimated values and current costs to date. 

AIA G702GMP-2021 and G703CW-2021

The form titles are:

  • G702CW-2021: Application and Certificate for Payment for Cost of the Work Projects without a Guaranteed Maximum Price
  • G703CW-2021: Continuation Sheet for Cost of the Work Projects

When to use: Contractors use these forms for cost-of-the-work contracts that do not include a guaranteed maximum price (GMP). In this type of agreement, the project owner reimburses the contractor for actual costs plus a management or overhead fee. Because there is no fixed price cap, the owner assumes responsibility for any cost overruns. This form pair suits projects with flexible budgets or projects where the total cost is difficult to estimate before construction begins.

How it’s different from G702/G703: The G702CW-2021 replaces “Contract Sum” with “Approved Control Estimate” since there is no guaranteed maximum price. It omits the “Balance to Finish” line because no set amount remains to reach a final total.

The contractor uses the same G703CW-2021 continuation sheet as in cost-of-the-work projects with a GMP. Together, these forms help owners and contractors manage open-ended budgets while maintaining accurate, transparent cost records each billing cycle.

AIA G742-2024 & AIA G743:-2024

The form titles are: 

  • AIA G742GMP-2024: Application and Certificate for Payment for a Design-Build Project
  • AIA G743GMP-2024: Continuation Sheet for a Design-Build Project

When to use: Contractors use these forms when they have a design-build contract, which is when a single company handles both the design and construction of the project. In this case, the design builder” will use this pair of forms to request payment for both design and construction activities. These forms apply specifically to design-builder contracts that have a GMP.

How it’s different from G702/G703: The G742 and G743 forms follow the same overall billing structure as the G702/G703 pair but adapt the language and layout to fit the design-build relationship. Because the design-builder performs both roles, they self-certify the G742-2024 pay application instead of submitting it to a separate architect for certification.

The G743-2024 Continuation Sheet works alongside the G742 to track each phase of design and construction. It includes space for detailed line items, cost categories, and progress tracking for both design services and field work.

Related AIA Invoice Forms

In 2024, the AIA expanded its design-build pay application series to include new forms that cover different contract setups, such as design-build agreements without a GMP and cost-of-the-work design-build contracts.

Here’s a quick overview of the other documents: 

  • G742CW-2024 and G743-2024: Cost-of-the-work design-build without a GMP. Note that design-build contracts use the same continuation sheet whether or not a GMP applies.
  • G742S-2024 and G743S-2024 – Subcontractor version for design-build projects.

AIA-style Templates and Examples You Can Download

Our free AIA-style templates, modeled on the G702 and G703 forms, walk you through preparing pay applications step by step. Each file includes a blank tab plus examples from mid-project and project completion, showing how values update over time. Templates come in Excel, Google Sheets, and other formats.

AIA-Style Template for G702 (Application & Certificate for Payment)

Here’s an example of an AIA-style Application & Certificate for Payment using our template.

Download the AIA-style pay application template:
Excel or Google Sheets

Our G702-style template includes all nine payment summary lines, certification and project detail sections, and automatic total calculations. You’ll also get a blank tab to fill in, an instructions tab, and filled-in AIA-style pay application examples from the middle and end of a project.

AIA-Style Template for G703 (Schedule of Values)

Our free AIA-style Pay Continuation template walks you through the process of filling out a pay continuation sheet like the AIA G703.

Download the AIA-style pay continuation template:
Excel or Google Sheets

Our G703-style template includes all standard columns from the G703, with sections for line items, work completed, stored materials, retainage, and balance to finish. You’ll also find AIA-style pay continuation examples showing how values update from mid-project through final billing.

How to Complete the AIA Billing Forms

To complete AIA billing forms, start with the G703. Enter each line item’s value, percent complete, and retainage. The total in Column G transfers to Line 4 on the G702. Then fill out the G702 to summarize the project’s progress and calculate the current payment due.

G703 Column-by-column Instructions

To complete the G703, list each line item from your schedule of values, then enter the scheduled value, work completed this period, and in prior periods, materials purchased but not yet installed, and retainage. These calculations give your total completed to date and the balance to finish.

The G703 Continuation Sheet includes ten columns (A–H) that track the progress of each line item from the contractor’s Schedule of Values (SOV). Each row represents one cost item or trade, and the contractor records how much progress has been made compared to the original amount the owner and contractor allocated for that item. The calculations in the G703 feed directly into the G702 Pay Application.

Here’s more about each of the columns (A - H) in the G703:

  • Item No: Use this column to identify each line item from your approved Schedule of Values (SOV). Most contractors use item numbers that match internal cost codes.
  • Description of Work: Provide a short description of the trade or scope of work, such as “Electrical,” “Framing,” or “Masonry.” Each line should clearly identify the task or phase of work represented by the cost item.
  • Schedule Value: Enter the total dollar amount originally budgeted for that line item. These figures come directly from the approved Schedule of Values (SOV) and remain the same unless your project owner adjusts them with an approved change order. Each item’s scheduled value forms the foundation for progress billing calculations.
  • Work Completed from Previous Application: List the cumulative amount billed for this item in all prior payment applications (G702 forms). This figure carries forward from the previous month’s G703 sheet. Tracking this value by trade or scope helps maintain a running total of progress and prevents double-billing.
  • Work Completed from Previous Application: Record the dollar value of work completed during the current billing cycle only.
  • Materials Presently Stored: Enter the total value of materials you’ve purchased, paid for, and have on-site or in approved storage, but haven’t installed yet. This lets you get reimbursed for those materials before installation. Once they’re installed, remove their value from this column.
  • Total Completed & Stored to Date: Add Columns D, E, and F. This total represents all the work you’ve completed and the materials you have stored on site up to the current billing period. Column G is critical because it feeds directly into Line 4 (“Total Completed & Stored to Date”) on the G702.
  • % Complete: Divide Column G (total completed and stored to date) by Column C (scheduled value), then multiply by 100 to show progress as a percentage.
  • Balance to Finish: Subtract Column G from Column C. That calculates how much work and budget remains for that item.
  • Retainage: List the portion of funds withheld for retainage, typically a set percentage (commonly 5–10%) of the total value completed to date. Some projects use variable retainage, where the retainage rate changes as the project progresses. For example, a contractor may apply 10% early in the project and reduce it to 5% after substantial completion.

G702 Line-by-line Instructions

To complete the G702, fill out each of the nine lines in order. Start with the original contract sum, add any adjustments, and calculate the total value. Transfer the total completed amount from the G703, then enter retainage, previous payments, and the current balance to finish.

The G702 form contains two major sections – the application for payment and the certificate for payment.

Here’s a line-by-line guide that walks you through both sections of a G702 form:

  • Contractors Application for Payment:
    The G702 has nine lines that summarize how much the contract is worth, how much the contractor has billed, and how much the owner owes this month. Each line builds on the last to show progress and the current payment due.

    Calculation:
  1. Original Contract Sum: Enter the total value of the signed contract.

    Example: $200,00

  2. Contract Sum to Date: Add Lines 1 and 2 to show the current total contract value.

    Example: $200,000 + $10,000 = $210,000

  3. Net change by Change Orders: Add or subtract any approved changes to the contract amount. For example, an owner might approve a $10,000 change to add a new structure.

    Example: +$10,000

  4. Total Completed & Stored to Date: Record the total value of work completed plus materials stored on-site but not yet installed. Find this number in Column G of the G703 form.

    Example: If the project is halfway complete, this may be $100,000.

  5. Retainage: Retainage is the portion of earned money the owner holds until project completion, usually 5–10%. Calculate it as a percentage of the total completed amount, not the entire contract sum.

    Example: 10% of $100,000 = $10,000

  6. Total earned Less Retainage: “Total earned less retainage” sounds confusing, but it simply means the total you’ve earned so far minus (or “less”) the amount being held back. To calculate it, subtract the retainage (Line 5) from your total completed amount (Line 4). This number shows your cumulative earned amount after accounting for retainage.

    Example: $100,00 - $10,000 = $90,000

  7. Less Previous Certificates for Payment: This line shows how much you’ve already been paid on previous applications. Most contractors can find this number in Line 6 of their last G702. If you’re using variable retainage, add the current payment due from each prior G702 instead of relying on Line 6 alone.

    Example: $60,000 (you’ve been paid $60,000 on previous applications).

  8. Current Payment Due: Now, subtract Line 7 (previous payments) from Line 6 (total earned less retainage). The result is your current payment due, or how much the owner owes you this month.

    Example: $90,000 - $60,000 = $30,000.
  1. Balance to Finish, Including Retainage: This line shows how much remains to complete the project. Subtract Line 6 (total earned less retainage) from Line 3 (contract sum to date). The result includes retainage and reflects the total value of work still remaining.

    Example: $210,000 - $90,000 = $120,000

  • Certificate for Payment: In this section, an architect or project supervisor certifies that the contractor’s reported progress and quality of work are accurate and reasonable. The certifier reviews the application and formally approves the payment application.

 

Examples of AIA-Style Bills

Below are two examples of completed AIA-style billing forms (not the licensed forms). The mid-project example shows how partial progress, retainage, and previous payments appear midway through a project. The final bill example shows how the contractor records 100% completion, releases retainage, and requests final payment to close out the job.

The AIA-style invoice examples appear in our AIA-style template downloads above.

AIA-Style Pay Continuation Invoice (G703-Style) Example for Mid-Project:

Here's how an AIA-style G703 Pay Continuation looks in the middle of a project.

In our mid-project example, the G703-style form tracks partial progress for each line item, showing how much labor the contractor has completed and what materials remain stored on site. The contractor carries those totals to Line 4 of the G702 to calculate the payment due for the month.

AIA-Style Pay Application Invoice (G702-Style) Example for Mid-Project:


Here’s a mid-project example of an AIA-style (G702) Application & Certificate for Payment from our template.

Download our G702-style template, linked above, and open the mid-project tab to see how contractors record partial progress, apply retainage, and calculate the payment due for that billing period.

AIA-Style Pay Continuation (G703-style) Invoice Example, Final Bill:

Here’s a final-project example of an AIA-style Pay Continuation Invoice from our G703-style template.

In our final bill example, the G703-style invoice shows 100% completion for all line items and releases any remaining retainage. Those totals roll into Line 4 of the G702, which calculates the final payment owed to close out the project.

AIA-Style Pay Application (G702-style) Invoice Example, Final Bill:

Here’s a final-project example of an AIA-style (G702) Application & Certificate for Payment from our template.

The final AIA-style pay application invoice example shows how the numbers flow into it to calculate the last payment.


Common AIA Invoice Mistakes to Avoid

Common AIA billing mistakes fall into three main types. Contract and value errors happen when change orders or totals are missing. Calculation errors occur when numbers on the G702 and G703 don't match, often from retainage or stored materials. Submission errors include missing signatures or blank fields.

FSH3: AIA Contract & Value Errors
Contract and value mistakes are common in AIA-style pay applications. They often happen when a contractor forgets to include approved change orders or enters the wrong contract total. These errors can make the forms inconsistent, delay approval, and cause payment disputes.

Here’s a list of typical errors that contractors make on the first few lines of their G702 and how to avoid them:

  • Forgetting to update the contract the month after approved change orders:
    “Contractors might forget to add the value of approved change orders to the pay app, which makes the total contract amount outdated,” explains Miller. “That mistake throws off every calculation based on the contract sum, including how much the contractor bills for that month.”

    To fix this issue, ensure that line 1 (“Original Contract Amount”) reflects the base contract only, while Line 2 (“Approved Change Orders – Net”) shows the total of all approved change orders to date. The total (Line 3) must match your adjusted contract amount in your agreement.

  • Billing unapproved change orders:
    “On the flip side, another common mistake is billing a change order before the owner approves it,” adds Miller. “In other words, they are billing for work or materials that relate to a change that is still pending, which usually inflates the pay request.”

    To fix this issue, Miller says it’s important to only include change orders with written, signed approval. “Keep pending changes in a separate internal log until the owner or architect formally approves them.

AIA Retainage and Calculation Errors

Retainage and calculation mistakes include using the wrong retainage rate, listing stored materials incorrectly, or carrying math errors from one pay app to the next. Because these figures affect the cumulative total, even a small mistake will throw off the numbers and delay payment.

Here’s a list of typical errors that contractors make when they’re calculating retainage and other fields across forms, and how to correct them:

  • Inconsistent retainage rates between forms
    Sometimes, the retainage percentage on the G703 doesn’t match the total on the G702. This issue often happens when the project owner releases retainage on a specific item, but the contractor doesn’t update that on their summary sheet.

    To fix this issue, apply retainage consistently across both forms. If your contract allows partial release, reflect those changes in both the line items on the G703 and the retainage total on Line 5 of the G702. The two forms must always reconcile, even when rates differ by item.

  • Incorrect carryover of previous applications
    This error occurs when the “Less Previous Certificates for Payment” line (Line 6 on the G702) does not match the total from the last approved pay application. When this line is incorrect, the current payment due becomes inaccurate, and the rest of the form’s calculations are thrown off.

    To avoid this issue, always double-check that you’re using the certified amount from your most recent approved G702.

  • Forgetting to update the “stored” materials
    “Contractors sometimes leave materials listed as ‘stored’ after they’ve been installed, which may cause them to double-bill for the cost of the materials,” explains Miller. “You only bill for stored materials once, but you keep showing that value in the ‘Stored Materials’ column each month until you install those materials. Once they are, you clear that line and roll the cost into prior work so the total stays accurate without double-counting."

    To fix this issue, make sure that once you install materials, you remove their value from the “Stored Materials” column on the G703. The cost of those materials will now roll into prior work, and the labor to install them will appear under “Work Completed This Period.” This practice ensures you’re billing correctly for the installation work without double-counting the material value.

  • Incomplete descriptions of line items in the G703:
    Contractors sometimes list broad categories like “General Work” or “Labor and Materials” across multiple lines. This makes it unclear which costs belong to which trade, and can even lead to double-billing if, for example, a contractor might accidentally bill electrical work under both “General Labor” and “Electrical.”

    To avoid this issue, make sure every line item matches the descriptions and divisions listed in the approved Schedule of Values. Each trade or phase should appear in the same order and with the same wording so the reviewer can trace each billed amount directly back to the contract.

  • The percentage complete doesn't match the progress:
    The “Percent Complete” field on the G703 sometimes doesn’t line up with the math — (Total Completed & Stored ÷ Scheduled Value), or with the actual progress on-site. Usually, this happens when the stored materials, change orders, or retainage are updated unevenly between the G702 and G703. It can also occur when contractors round percentages instead of using exact figures, which throws off cumulative totals.

    To avoid this error, recalculate the percentage complete for each line using the correct formula and confirm that it matches both your field progress and the cumulative totals on the G703. Use precise numbers instead of rounding. 

AIA Billing Submission and Documentation Errors

Some AIA billing mistakes happen because the contractor doesn’t finish the paperwork, not because the math is wrong. Common problems include missing receipts, proof of stored materials, or approved change orders. Another is forgetting to get the architect’s or owner’s signature on the form.

  • Missing supporting documents
    Most pay applications require contractors to include supporting documents to validate their charges. For example, a contractor might list the value of stored materials on the G703 but forget to attach proof such as receipts, delivery slips, or photos showing that the materials are on-site or in approved storage.

    Many contracts also require the contractor to submit a lien waiver, which is a legal document confirming that the contractor has been or will be paid, protecting the project owner from future claims. When any of these documents are missing, the architect is likely to flag the pay application and delay payment until everything is complete.

    To address these issues, always double-check that you’re attaching the relevant supporting materials, like a proof of purchase for any materials you are billing as “Stored.” Also, check your contract to see whether the project owner requires you to submit a lien waiver or an insurance certificate for off-site items.

  • Wrong signature authority or incomplete signature:
    Since AIA forms are official certifications, only authorized signatories identified in the contract can sign the G702 and certify the payment application.

    “Owners and architects are strict about signatures,” says Miller. “An unsigned pay app is treated like it was never submitted.”

    To avoid this issue, confirm who is authorized to sign on behalf of your company before submitting. Make sure all required parties, like the general contractor and architect, have signed in the correct spaces before sending the pay application for approval.

AIA Billing Checklist

Download the free AIA Pre-Submission Checklist to double-check your pay app before sending it in. Catch small errors early, avoid payment delays, and keep your billing running smoothly.

AIA Invoicing Options for Digital Submission and Automation

Today, contractors can complete and send AIA billing forms electronically. They can use the AIA’s online tools, editable PDF forms, or other software that works with AIA forms. A good digital tool lets users sign forms electronically and performs automatic calculations. These tools help contractors save time, reduce mistakes, and get paid faster.

Digitally submitting AIA forms is more than just convenient – many platforms offer project management services that help large and small firms alike manage their overall AE billing and invoicing workload.

Here’s a breakdown of the most common ways to complete and submit AIA Forms:

  • The AIA Contract Documents Online Service
    The AIA hosts its own cloud platform that allows contractors and project owners to prepare and manage contract and billing forms, including the G702 and G703. It’s a subscription-based service that comes with official AIA templates. Users can fill out the forms online via a web interface.

    The platform supports version tracking, cloud collaboration, and includes integrated e-signatures. For example, a contractor and architect can sign and certify each G702 pay app directly in the platform. Overall, AIA’s own solution guarantees you are using up-to-date official documents and simplifies the signing and printing process, albeit at a licensing cost.

  • Third-party platforms for digital AIA billing
    Beyond the official AIA platform, several third-party platforms make it easier to handle AIA billing. Some focus purely on generating AIA-style pay applications, while others integrate these forms into broader project management and billing systems.

    When choosing third-party software for AIA billing, look for tools that simplify pay application preparation rather than just providing blank forms. The best options include built-in AIA templates that automatically calculate totals, retainage, and balances due to reducing the chance of manual errors

    It also helps if the software can track revisions and approvals, so you always know whether a pay app is submitted, reviewed, or paid. Some systems can generate professional PDF exports and keep a clear record of each payment period. Ideally, the platform should integrate with your existing accounting or project data and allow the architect or contractor to digitally sign and certify the pay apps.

  • Editable templates:
    Many contractors, especially smaller firms, use editable templates to prepare their G702 and G703e forms instead of purchasing dedicated software. You can buy official, fillable PDFs directly from the AIA, which are licensed for a single project.

    Using these forms is convenient, but it’s important to remember that official AIA documents are copyrighted and come with licensing restrictions. Beyond the official AIA forms, several industry websites offer a free G702/G703-style template.

    For many small businesses, the practical approach is to start with a free Excel version and purchase the official AIA forms if the client or lender requires them.

Simplify Architect Invoicing with BQE CORE

Architecture firms juggle multiple billing methods — fixed-fee, hourly, milestone, and progress-based billing, to name a few — and BQE CORE streamlines all of it. The platform centralizes contracts, budgets, time and expenses, and project financials so firms can produce accurate invoices without chasing spreadsheets or reentering data.

CORE’s customizable invoice formats make it easy to build professional invoices that reflect your contract structure, support percent-complete billing, and incorporate schedules of values, retainage, and approved change orders. And even if a project requires licensed AIA forms issued outside of CORE, the system still handles the underlying calculations and progress tracking that make those documents accurate.

Built-in e-payment options help shorten collection cycles, while real-time dashboards show how billing performance affects profitability and utilization across every active project. With CORE, firms get a faster, more organized way to manage architect invoicing — no matter how each contract is structured.

Video: How BQE Simplifies Architect Invoicing


In this video, we walk you through architecture invoicing in BQE CORE.

FAQs on AIA Billing and Invoicing

Do I need a Schedule of Values when using AIA billing?

Yes, most projects that use AIA billing require a Schedule of Values (SOV). It serves as the foundation for progress billing by breaking down the total contract sum into parts. Without it, you can’t accurately complete or update the G703 continuation sheet.

What is the difference between a Schedule of Values and a Continuation Sheet?

A Schedule of Values (SOV) breaks down the total contract sum into specific values for each phase or trade. The contractor and project owner create the SOV before work begins. The Continuation Sheet (G703) draws from the SOV to show how much of each phase is complete and what remains.

Can I submit AIA forms digitally?

Yes, you can submit AIA forms digitally. Many contractors complete and send G702 and G703 forms through licensed AIA software or compatible platforms that follow official templates. However, always confirm the specific payment process with the project owner.

Are AIA forms required on all projects?

No, AIA forms aren’t required on every project. They’re only needed when the contract states that billing must follow the AIA format. Many construction projects that use progress billing include this requirement, especially if an architect is involved.

For more, see our ultimate guide to AE billing and invoicing